A roof Sika made into a case study.
AIS Arena, ACT · Arena roof replacement
We put a new Sika Sarnafil roof over 6,500m² of the Australian Institute of Sport Arena in Canberra. Sika then published it as a case study in best-practice Sarnafil installation.
- Location
- Canberra, ACT
- Building
- Australian Institute of Sport Arena
- Duration
- 14 months
- Value
- $5M
- System
- 2mm fleece-back Sika Sarnafil, fully bonded
6500m²
Of new roof
14
Months on site
$5M
Of works
The challenge
An arena roof is vast, with long gutter runs and drainage across the whole of it. The new roof had to go on as one seamless system, to the manufacturer’s own standards.
Our response
We laid 2mm fleece-back Sika Sarnafil membrane, fully bonded, over the whole roof, made custom half-pipe drain diverters, and lined every gutter so the roof works as one seamless system.
Scope of works
- 016,500m² of 2mm fleece-back Sika Sarnafil membrane, fully bonded
- 02Custom-fabricated half-pipe drain diverters
- 03Every gutter lined
- 04One seamless system across the roof
Published by Sika as best practice.
Next case study · BombalaWaterproofing that went in before the building did.