Live, occupied, staged
The building was wrapped and worked on in stages while residents lived in it, with detailed communication throughout and the external works coordinated around access to every apartment.

Cremorne, NSW · Facade, waterproofing, windows, doors & balustrades
A major Class 2 residential upgrade: balcony re-waterproofing, suspended paving, new windows, doors and structural glass balustrades, facade remediation and protective coatings, all in a fully occupied building.
$4.5M
Project value
13
Months on site
9
Scopes of work, one builder
Failing waterproofing had caused chronic water penetration. Windows and doors were affected and no longer working as they should. Non-compliant balustrades on the roof and balconies were a significant safety risk, and cracking and concrete spalling on the facade were shortening the life of the building.
SRS worked with the consultant team and specialist contractors to address all of it at once. Staged works, detailed resident communication and careful coordination between the external envelope and internal access kept a fully occupied building running throughout.


The building was wrapped and worked on in stages while residents lived in it, with detailed communication throughout and the external works coordinated around access to every apartment.
The non-compliant balustrades on the roof and every balcony came out, replaced with toughened laminated glass on polished stainless steel stand-offs with interlinking handrails, all to current codes.
Every window and door was replaced with units that meet or exceed current codes for wind load and water pressure: AWS systems made in regional NSW on a new production line, in a custom long-life powder-coat colour.
A logistically challenging project and an outstanding team effort, delivering a renewed facade and living spaces for residents to enjoy for many years to come.