Every roof, terrace and balcony, with everyone still at home.
Wollongong, NSW · Full building remediation
We’re carrying out a full remediation of an occupied apartment building in Wollongong: re-waterproofing the roof, terrace and balconies, remediating the facade, rebuilding the glass block windows and putting in new basement drainage.
- Location
- Wollongong, NSW
- Building
- Apartment building, fully occupied
- Programme
- 10 months, under way
- Value
- $2.5M
- Access
- Mast climbers and swing stage
10
Month programme
$2.5M
Contract value
The challenge
The whole roof, along with every terrace and balcony, needs re-waterproofing, and the existing rendered facade is falling off in sheets and in desperate need of remediation.
Our response
We’re re-waterproofing every roof, terrace and balcony in Fatrafol 807 fleece-back PVC membrane, remediating the facade with the Dulux Acratex system, rebuilding the fire-rated glass block windows and putting in new basement stormwater drainage. We’re working from mast climbers and a swing stage, so the building stays fully occupied with little to no disruption to the residents.
Where it started.
Scope of works
- 01Re-waterproofing the roof, balconies and terrace in Fatrafol 807 fleece-back PVC
- 02Complete facade remediation
- 03Rebuilding the fire-rated glass block windows
- 04New basement stormwater drainage
- 05Mast climber access provided by SAS Australia
Large-scale, multi-trade work in an occupied building is what we do best.