Wollongong, NSW · Full building remediation

We’re carrying out a full remediation of an occupied apartment building in Wollongong: re-waterproofing the roof, terrace and balconies, remediating the facade, rebuilding the glass block windows and putting in new basement drainage.

Location
Wollongong, NSW
Building
Apartment building, fully occupied
Programme
10 months, under way
Value
$2.5M
Access
Mast climbers and swing stage

10

Month programme

$2.5M

Contract value

The whole roof, along with every terrace and balcony, needs re-waterproofing, and the existing rendered facade is falling off in sheets and in desperate need of remediation.

We’re re-waterproofing every roof, terrace and balcony in Fatrafol 807 fleece-back PVC membrane, remediating the facade with the Dulux Acratex system, rebuilding the fire-rated glass block windows and putting in new basement stormwater drainage. We’re working from mast climbers and a swing stage, so the building stays fully occupied with little to no disruption to the residents.

Where it started.

Scope of works

  1. 01Re-waterproofing the roof, balconies and terrace in Fatrafol 807 fleece-back PVC
  2. 02Complete facade remediation
  3. 03Rebuilding the fire-rated glass block windows
  4. 04New basement stormwater drainage
  5. 05Mast climber access provided by SAS Australia

Large-scale, multi-trade work in an occupied building is what we do best.