Carpark entrance with red and white tape across the driveway and fresh asphalt
← All projects

Award-winning repairs to a critical substation.

North Sydney, NSW · Waterproofing & concrete repair

In five weeks we stopped the water getting into a North Sydney substation, protected and repaired its concrete, and made a 1.6-tonne access hatch for the job. It won an ACRA Award.

Location
North Sydney, NSW
Building
Electrical substation
Duration
5 weeks
Value
$300k
Recognition
ACRA Award

5

Weeks on site

1.6t

Access hatch, made for the job

$300k

Of works

A substation is critical infrastructure. Water had to be kept out for good, and every step needed careful planning and tight safety controls.

We waterproofed the structure against water entry, installed sacrificial anodes to protect the reinforcement, repaired the concrete, laid hot-mix asphalt and manufactured a 1.6-tonne access hatch.

Where it started.

Scope of works

  1. 01Waterproofing and water entry mitigation
  2. 02Sacrificial anode installation
  3. 03Concrete repair
  4. 04Hot-mix asphaltic concrete
  5. 05A 1.6-tonne access hatch, manufactured for the job

Five weeks, and an ACRA Award.

Next case study · ManlyA whole-building upgrade, from a tower crane and mast climbers.