Make it safe
Short-notice scaffold and Shore 400 series emergency props took the load first.

Greenwich, NSW · Structural strengthening
The undercroft of an occupied five-storey apartment building in Greenwich had decayed to the point of danger. We propped it at short notice, then strengthened it for good.
The structure in the undercroft had decayed badly. Left much longer without proper repairs, a catastrophic failure was a real possibility, with residents living above.
We put up scaffold and emergency propping at short notice. Then we cast reinforced high-strength jackets around the columns to restore and increase their strength, strengthened the beams (including with carbon fibre) and repaired the spalling concrete.
Short-notice scaffold and Shore 400 series emergency props took the load first.
Reinforced high-strength column jackets restore the columns and add strength. Beams were strengthened, with carbon fibre where needed, and spalling repaired throughout.
Made safe first, then made stronger.
Next case study · ChatswoodBalconies that finally stay dry.